The Town of Mocksville operates an extensive water system providing service to customers. The Madison Road Booster Pumping Station is equipped with two booster pumps, one of which must  operate at all times to maintain system pressure to customers north of Interstate 40.

To improve the reliability of the Pumping Station, Willis Engineers identified several needed improvements; the installation of a smaller pumping unit to reduce wear on the main pumping unit, the replacement of the existing control panel, and new flow meters to improve operational control. The project was completed in early July 2017, under budget at a cost of approximately $104,000.