Sealed Bids for the construction of the Contract 1.0 – Clearwell, High Service Pump Station and Water Line will be received, by Cleveland County Water at the Administration Building, 439 Casar Lawndale Road, Lawndale, North Carolina 28090, until 2:00 PM local time on January 28, 2021, at which time the Bids received will be publicly opened and read.  The Project consists of construction of a 3.0 million-gallon clearwell, high service pump station and associated piping, approximately 1,460 feet of 16-inch water line and all appurtenances. 

Bidding Documents may be obtained from Duncan Parnell (www.dpibidroom.com) for a purchase price as listed on their website.  All payments are to be made to Duncan Parnell.  Prospective bidders must purchase Bidding Documents directly through Duncan Parnell in order to be considered an official plan holder.  Neither Owner nor Engineer will be responsible for full or partial sets of Bidding Documents, including Addenda if any, obtained from sources other than the Issuing Office.

A pre-bid conference will be held at 10:00 am local time on Wednesday, January 13, 2021 at the Water Treatment Plant, 437 Casar-Lawndale Road, Lawndale, North Carolina 28090.  Attendance at the pre-bid conference is highly encouraged but is not mandatory.

Construction Estimate: $7,700,000

Plan Holders List can be found on the Duncan Parnell website listed above.  

Addendum No. 1 Issued January 21, 2021