Sealed Bids for the construction of Contract 15.0 – Crestline Pump Station Renovation were be received by the City of Laurinburg on January 10, 2023, at which time the Bids received were publicly opened and read.  The Project consists of a complete renovation of the Crestline Pump Station, including new pumps, valves, piping, wet well coating, electrical equipment, and site improvements.   

Apparent Low Bidder: Step Construction – Bid Tab

Awaiting Award of Contract 

City of Laurinburg – Crestline Pump Station Renovation

Sealed Bids for the construction of Contract 13.0 – Distribution System Improvements Phase 2 were received by the City of Laurinburg on November 22, 2022, at which time the Bids received were publicly opened and read.  The Project consists of constructing approximately 10,400 feet of 20-inch water line, 640 feet of 16-inch water line, 850 feet of 12-inch, 1,340 feet of 8-inch, and 320 feet of 6-inch water line and all appurtenances. 

Apparent Low Bidder: Metcon, Inc. – Bid Tab

Construction Anticipated Summer 2023

 

City of Laurinburg – Distribution System Improvements Phase 2

Sealed Bids for the construction of the Contract 4.0 – East Marion Street Booster Pump Station were received by Cleveland County Water on November 17, 2022 at which time the Bids received were publicly opened and read.  The Project consists of constructing a booster pumping station, demolition of two booster pump stations and all appurtenances.

Apparent Low Bidder: Brushy Mountain Builders – Bid Tab

Construction Anticipated Summer 2023

 

Cleveland County Water – East Marion Street Booster Pump Station

Sealed Bids for the construction of the Contract 15.0 – Bear Creek Pump Station Improvements were received by the Town of Mocksville on Tuesday, May 17, 2022, at which time the Bids received were publicly opened and read.  The Project consists of improvements to the Bear Creek Pump Station including the addition of a third pump and associated electrical equipment.

Awarded to Gilbert Engineering – Bid Tab

Construction Anticipated Summer 2023

 

Town of Mocksville – Bear Creek Pump Station Improvements

Sealed Bids for the construction of the Contract 12.0 – Pump Station, Force Main, and Water Line were received, by the Town of Mocksville on Tuesday, May 17, 2022 at which time the Bids received were publicly opened and read.  The Project consists of constructing approximately 10,155 linear feet of 8-inch force main, 688 linear feet of 8-inch gravity sewer, 1,803 linear feet of 12-inch water line, a new duplex pump station, and all appurtenances.

Awarded to Baker Underground – Bid Tab

Currently Under Construction

Town of Mocksville – Utilities to Serve Brakebush Brothers

Sealed Bids for the construction of Contract 12.0 – Influent Pump Station Improvements were received by the City of Laurinburg on Thursday, March 3, 2022, at which time the Bids received were publicly opened and read. The Project consists of constructing a new headworks and influent pump station and associated piping and site improvements.  The project also includes demolition of existing facilities.

Awarded to Dellinger, Inc. – Bid Tab

Currently Under Construction

City of Laurinburg – Leith Creek WWTP Influent Pump Station

Sealed Bids for the construction of Contract 82.1 – Gravity Sewer and Force Main Phase II were received by the Town of Mooresville on September 2, 2021, at which time the Bids received were publicly opened and read.  The Project consists of constructing 12,500 feet of 24-inch force main and 9,635 feet of gravity sewer ranging in size from 8-inch to 36-inch. The work includes decommissioning of the Cherry Grove Pumping Station and Panasonic Pumping Station.

Awarded to Hall Contracting Corporation – Bid Tab

Currently Under Construction 

Town of Mooresville – Gravity Sewer and Force Main Phase II

Sealed Bids for the construction of Contract 15.0 – South Gateway Area Pump Station and Force Main were received by the City of Mount Holly on February 18, 2021, at which time the Bids received were publicly opened and read.  The Project consists of constructing approximately 9,100 linear feet of 12-inch force main, 325 linear feet of 8-inch and 16-inch gravity sewer, a new triplex pump station and all appurtenances.

Awarded to Two Brothers Utilities, LLC. – Bid Tab

Currently Under Construction 

City of Mount Holly – South Gateway Area Pump Station and Force Main

Sealed Bids for the construction of the Contract 1.0 – Clearwell, High Service Pump Station and Water Line were received by Cleveland County Water on January 28, 2021, at which time the Bids received were publicly opened and read.  The Project consists of construction of a 3.0 million-gallon clearwell, high service pump station and associated piping, approximately 1,460 feet of 16-inch water line and all appurtenances. 

Awarded to Dellinger, Inc. – Bid Tab

Currently Under Construction 

Cleveland County Water WTP Clearwell, High Service Pump Station and Water Line

Sealed Bids for the construction of Contract 81.0 – Pump Station were received by the Town of Mooresville on November 19, 2020, at which time the Bids received were publicly opened and read.  The Project consists of constructing a new wastewater pumping station and all appurtenances on Wiggins Road in Mooresville.

Awarded to Hall Contracting Corporation – Bid Tab

Currently Under Construction

Town of Mooresville – Wiggins Road Sewer Facilities, Pump Station